Thursday 06 August 2020
Banner #11

Rajagopuram

 

 

Hindu Temple and Cultural Center of Kansas City is proud to see community coming together to add Rajagopuram to Temple. This will give Temple a landmark identity and bound serve our future generation in understanding their heritage. This page will provide progress towards the project.

Scroll further to check on Rajagopuram expansion project updates.


  • Work in progress More idols  
  • Dwajasthamba sections and Door panels being made.
Date: 07/06/20
     
 

  •   Ground sodded with grass
Date: 06/11/20
   

  • Paint/Sealing/Striping work complete
Date: 06/11/20

  • Gopuram Kalasas ready.
  • More finishing work - Sprinklers restored and working
Date: 06/10/20    
 

  • Construction tasks almost complete and now has a better view.
  • Electrical work also getting to completion stage.
Date: 06/03/20
 
 

 


  •  Landscape and Lighting walls complete
Date: 05/26/20
 

 


  • Landscape walls and Light pole base setup work in progress
Date: 05/21/20
 

  •  Area around Rajagopuram getting more updates
  • Dwajastamba plantes are being made
  • Dwajastamba carving in the works.
Date: 05/10/20
 
   
   

 


  • Completed ADA ramp, Gopuram floor, Main door, Front pavement, Parking complete
  • Front landscape area in progress

 

Date: 05/07/20
 
     

  •  Front pavement getting ready
  • ADA ramp getting ready
Date: 05/02/20

 


  •  Finished Rajagopuram structure
  •  Courtyard pavement complete
Date: 04/25/20
 
 

 

  •  Final level completed, pavement inside and south complete, electrical work in progress
  • Door work in Progress
Date: 04/17/20
 

  • Additional levels of Rajagopuram progressing
  • Final level and concrete pavement (walking area) in progress
Date: 04/11/20

  • Rajagopuram getting levels and more sculptures in the works.
Date : 04/05/20

  • Sculptures being made
Date: 04/02/20

  •  Side wall getting finishing touches
Date: 03/12/20

  • First level roof completed
Date: 03/03/20
 
     

  • Rajagopuram level-1 roof to be poured
  • CMU wall on the East side to continue
  • Concrete paving to start inside Rajagopuram courtyard
  • Pour slab for flower beds
  • Dwajasthambam and Door work is in progress
  • Kumbhabishegam committee formed and conducting periodic meeting
  • Stapathi VISA process - USCIS is expected to conduct site visit in end of April
Date: 02/28/20

 


  • Rajagopuram footing to be poured tomorrow
  • CMU wall on the East side to continue
  • Back fill dirt
  • Pour slab for flower beds
  • Start Rajagopuram CMU wall
  • Dwajasthambam and Door work is in progress
  • Kumbhabishegam committee formed and conducted first meeting last week
Date: 02/20/2020
 

 


  •  Perimeter CMU walls in progress
  •  Helical piers are completed, ready to pour foundation
  •  PSI inspector on site as and when needed, reports are being reviewed by our architect
  •  Dwajasthambam footing completed
  •  CMU walls on the east will follow next week
  •  DFC has set up a spread sheet / calendar to show work progress and inspections dates.
  •  Kalasams are being ordered from Kumbhakonam, Tamil Nadu
  •  24 concrete idols to go on Rajagopuram is being made by our Stapathi Ravindran in Coimbatore, Tamil Nadu
Date: 01/31/2020

  • CMU  wall work in progress
Date: 01/16/2020

 


  • Concrete walls being done today. Helical piers area to follow
  • We have a PSI inspector on site as that's being done today.
  • Scheduling the installation of three more helical piers and will have PSI on site during the install.
  • Crew coming in to start the CMU walls and
  • Randy will coordinate all inspections.
Date: 01/09/2020

 

  • Forming for wall, flagpole foundation, helical piers install in progress
Date: 01/08/2020
 

 

  • Foundation ready to install helical piers
  • Reinforcement rods being placed 
Date: 01/06/2020

 

  • CMU blocks arrived
  • Concrete being poured for Foundation footing
  •  Electricians will be working to set up all wiring in the coming weeks
  • Install of the Helical piers.
  • Installation of additional foundation walls in the coming week
  • Installation of CMU walls- to follow- depends on weather
  • Randy Cluck is the superintendent on site
Date: 12/27/2019

 


  • All iron work ready for pouring foundation
Date:12/25/2019

 

  • Drain pipe 50% complete
  • Iron work for wall footing in progress
  • Dwajasthambam excavation in progress
  • Ramp footing in progress
  • Electrical demolition completed
Date:12/21/2019

 

  • Construction work underway on footings, plumbing
  • Excavation for  footing and electrician will follow.
  • CMU walls should be starting in two weeks
  • Helical piers will be installed by Custom Concrete
  • Specs for piers - to follow
  • DF Constrution LLC has been given the construction contract for our project.
Date:12/17/2019

 

SHLOKA

When I Asked God for Happiness
He Showed Me Some Unhappy People

When I Asked God for Brain & Brawn
He Gave Me Puzzles in Life to Solve

When I Asked God for Strength
He Gave Me Difficult Situations to Face

When I Asked God for Wealth
He Showed Me How to Work Hard

When I Asked God for Favors
He Showed Me Opportunities to Work Hard

When I Asked God for Peace
He Showed Me How to Help Others

God Gave Me Nothing I Wanted
He Gave Me Everything I Needed

"Tribhirgunamayairbhavairebhih Sarvamidam Jagat
Mohitam Nabhijanati Mamebhyah Paramavyayam"

The whole world is engrossed in the three elements of Satva, Raja, and Tama. This is the reason, people don't recognize the Eternal God who is beyond them.

Copyright 2020, Hindu Temple & Cultural Center of Kansas City,
All rights reserved.

Site Designed by designthemes.com

Connect with us Twitter Facebook

Quick Contact

Hindu Temple & Cultural Center of Kansas City
6330 Lackman Road, Shawnee, KS 66217-9739

Phone: (913) 631-7519
Email: managers@htccofkc.org

Web Master:  SabkaSai@gmail.com